South32 Worsley

CELB shared-resources model across scaffolding, NDT and sheetmetal, blast & paint

Reporting Window
Jul '26 – Sep '27
Current Month
June 2026
Model Commencement
01 Jul 2026
Last Refreshed
2026-06-19
Phase Scaffolding NDT Sheetmetal/Blast/Paint Discipline Scaffolding Cranage / Hoists Strip & Recovery Roster
01Portfolio — Key MetricsWorkforce, safety & rollout across the shutdown cycle
Workforce on site
38 / 41
93% availability · 5×10 roster
VOC / Pegasus current
100 %
all crew verified
Rollout progress
34 %
Phase 1 — Scaffolding mobilising
Days since LTI
214
TRIFR 0.0 (rolling 12m)
02Scaffolding Demand by Campaign × MonthPeak daily required vs filled across the shut cycle

Source: SRG planning board (peak daily required vs filled), bucketed by shutdown commence month. A retained core absorbs the troughs; cells show filled/required with fill-rate %.

CampaignJUL '26AUG '26 SEP '26OCT '26NOV '26TOTAL
MFC combustor build 53/75 (71%) 53/75 (71%)
110 boiler shutdown 50/55 (91%) 50/55 (91%)
Calciner campaign 44/48 (92%) 44/48 (92%)
Strip & recovery (core) 38/38 (100%)38/38 (100%) 38/38 (100%)38/38 (100%)38/44 (86%) 190/196 (97%)
GREEN ≥ 90% filled AMBER 70–89% RED < 70%
03Shared-Resources Model Rollout34% complete
Done 18% Active 16% On track 24% At risk 8% Planned 34%
04Latest Site Update
Fri 19 Jun 2026 · Day shift · Scaffolding core team

Maintenance scaffolding mobilisation — week 3

Core crew of 38 on site (5×10 roster). Strip campaign on calciner access ahead of plan; two long-standing scaffolds cleared using shutdown hoists, recovering ~14 t of trapped Layher material back to the yard.

MFC combustor build pack walked down with planning ahead of the July shut. No safety events; one hazard observation raised and closed (housekeeping, L3 landing).

No injuries0 environmental 38 on site14 t recovered1 hazard obs (closed)
05Workforce & Safety — This Week
Hours worked (wk)
1,710
▲ 5×10 roster live
Availability
93%
3 on leave / RDO
Inductions (wk)
4
retained core — low churn
Near misses
0
2 hazard obs raised
Material recovered
14 t
via shutdown hoists
Access utilisation
88%
scaffold & rope access
06Phased Rollout — One Shared StructureSPA led by Emile Muller, Area Manager — CELB

Specialist services brought together under a single CELB structure, introduced in three phases — each built directly around the structural inefficiencies set out in the business case.

Phase 1 · Core

Scaffolding

  • Maintenance & shutdown scaffolding planned as one scope
  • Quiet periods become strip campaigns; clear long-standing scaffolds
  • Shutdown cranage & hoists recover trapped material
  • Retained core carries site knowledge on high-risk builds
Live — from Jul 2026
Phase 2 · Extend

NDT

  • Specialist capability shared across sites
  • Smoother scheduling, higher equipment & people utilisation
  • Inspection aligned to shutdown execution windows
Planned — Q1 2027
Phase 3 · Scale

Sheetmetal, Blast & Paint

  • Scalable multi-discipline support model
  • Continuity between work fronts; capability shared on demand
  • Operational & commercial efficiencies across campaigns
Planned — Q3 2027
07Milestone RegisterShutdown campaigns & rollout milestones
Milestone / campaignWindowPeak labourStatus
Shared-resources model commencement01 Jul 2026Core 38Active
MFC combustor buildJul 2026 · 1 week15 / shiftOn track
110 boiler shutdownAug 2026 · 1 week12 / shiftOn track
Calciner campaignSep 2026 · 2 weeks6 / shiftPlanned
EA transition / Muja release windowNov 2026Watch
Phase 2 — NDT integrationQ1 2027TBCPlanned
Phase 3 — Sheetmetal, blast & paintQ3 2027TBCPlanned
08Rollout & Campaign ScheduleColour-coded by status with progress fills
Activity Jul 26Aug 26Sep 26 Oct 26Nov 26Dec 26 Q1 27Q2 27Q3 27
09Labour Demand & Access OutlookDemand smoothing — anticipated, not just reported

Demand fluctuates sharply across the cycle. The shared model smooths the peaks against a retained core, turning the troughs into strip and recovery campaigns. Forecast peak shifts are flagged against the campaign they belong to.

Wk 23
38
Core · strip
Wk 26
53
MFC combustor (+15)
Wk 31
50
110 boiler (+12)
Wk 36
44
Calciner (+6)
Wk 40
38
Core · clear standing
Wk 44
38
Core · recovery
Wk 47
38
EA transition watch
Why it matters: a four-day week pushes work into Friday penalty rates and the tail of a 12-hour day is rarely productive. The model moves to a five-day, 5×10-hour roster — removing both — and holds a retained core so peaks are met without the onboarding cost of cycling crews up and down.
10Assumptions, Constraints & Key Personnel
Assumptions & constraints
  • · Management, supervision, HSE & admin overhead absorbed within SRG's existing Worsley shutdown scope — nil additional charge.
  • · Five-day week, 5×10-hour shifts; Friday penalty exposure removed.
  • · Option 1 (local labour) requires visa-supported resourcing while the Muja shut runs to Nov 2026.
  • · Lifts already exist in target facilities; shutdown cranage & hoists shared for material recovery.
  • · EA transition window — optional $5,000 retention incentive to protect against industrial action.
Key personnel
  • · Mark Cowle — General Manager, Southwest (SRG Global)
  • · Emile Muller — Area Manager, CELB (SPA lead)
  • · Shutdown Superintendent — existing shutdown structure
  • · HSE Advisor — existing shutdown structure
  • · Maintenance Supervisor & Leading Hand — beneath existing coordinator
  • · Jeremy Gledhill — South32 Worsley Alumina (client contact)
11Commercial SummaryIndicative · exclusive of GST

As requested, indicative costings. Overhead and plant to run the model are absorbed within SRG's existing shutdown scope at no additional charge to South32.

DescriptionOpt 1 · Local + visaOpt 2 · Perth + LAHA
Execution labour$2,246,994$2,298,672
Equipment$275,239$275,239
Disbursements, LAHA & mobilisationNil$45,750
Overhead (super, HSE, admin)$0$0
Total (ex GST)$2,522,233$2,619,661

Option 2 carries +$97,427 over Option 1, driven by labour. Optional early-mobilisation retention incentive of $5,000/head available through the EA transition.

Proposed volume rebate (banded on annual spend)
Annual spendRebate
$14m1.25%
$16m1.50%
$18m1.75%
$20m2.00%

Worst case the banding shifts down by $1.5m — to $12.5m / $14.5m / $16.5m / $18.5m — at the same rebate percentages.

01Shift Report FeedContinuous, dated — no gaps

A continuous, dated feed of execution shift reports — safety status, manning, progress, forecast work and any concerns. Days with no work are shown so the record is complete.

Fri 19 Jun 2026 · Day shift

Maintenance scaffolding mobilisation — week 3

Safety: No injuries, no environmental events. One hazard observation (housekeeping, L3 landing) raised and closed same shift.

Manning: 38 of 41 rostered on site (5×10). 3 on approved leave/RDO.

Progress: Calciner strip campaign ahead of plan; two long-standing scaffolds cleared with shutdown hoists, ~14 t Layher recovered to yard. MFC combustor build pack walked down with planning.

Forecast: Continue calciner strip; begin MFC combustor pre-fab staging Monday.

No injuries38 on site14 t recovered
Thu 18 Jun 2026 · Day shift

Strip campaign & material recovery

Safety: Nil events. Pre-start focus on dropped-object prevention during dismantling at height.

Manning: 39 on site. VOC/Pegasus verification confirmed current for all crew.

Progress: Cleared standing scaffold at the No.4 unit; hoist recovery removed double-handling. Maintenance ply and gap protection upgraded on two work fronts using existing carpentry labour.

Forecast: Continue recovery; planning walk-down for MFC combustor tomorrow.

No injuries39 on site100% VOC current
Wed 17 Jun 2026

No Work — site stand-down (planned RDO)

Planned roster day off. No crew on site. Record retained for completeness.

No Work
Tue 16 Jun 2026 · Day shift

Core team onboarding & planning integration

Safety: Nil events. Two hazard observations raised (access gate, lay-down housekeeping), both closed.

Manning: 41 on site including 4 new inductions completed (Layher, site familiarisation).

Progress: Integrated maintenance + shutdown scaffolding plan loaded into the OMS. First combined look-ahead issued; better-planned areas no longer queued behind last-minute execution.

Forecast: Begin calciner strip campaign Thursday.

No injuries41 on site2 hazard obs (closed)
Mon 15 Jun 2026 · Day shift

Shared-resources model — week 3 kickoff

Safety: Nil events. Weekly safety interaction held on dropped objects and exclusion zones for hoist recovery.

Manning: 37 on site; 5×10 roster confirmed across the core team.

Progress: Confirmed shutdown cranage/hoist availability for material recovery. Reviewed MFC combustor (15/shift), 110 boiler (12/shift) and calciner (6/shift) labour profiles against the retained core.

Forecast: Complete inductions; finalise integrated look-ahead.

No injuries37 on site
01Controlled Project RegisterLatest revisions · downloadable on demand

The controlled register for the CELB shared-resources engagement — proposal, commercial, reporting, compliance, safety and quality.

Proposal & commercial
CELB Shared Resources Business Case — South32 Worsley Issued

Letter of Offer and business case setting out the proposed overhead structure, opportunities and benefits, indicative costings and a volume-rebate structure. Addressed to Jeremy Gledhill, South32 Worsley Alumina, June 2026.

Business_Case_CELB_Worsley_Jun2026.pdf Letter_of_Offer.pdf
Commercial summary & indicative costings Issued

Option 1 (local labour + visa support): $2,522,233 ex GST. Option 2 (Perth labour + LAHA): $2,619,661 ex GST. Overhead returned at zero. Volume rebate banded 1.25%–2.00% on annual spend.

Costings_Options_1-2.xlsx Volume_Rebate_Schedule.pdf
Figure 1 — Proposed CELB shared-resources structure Issued

Org structure: maintenance scaffolding folded beneath the existing Worsley shutdown structure. Superintendent, HSE advisor and administration lines returned at zero cost.

CELB_Org_Structure.pdf
Reporting & governance
Live reporting platform — scope & access Live

Reporting delivered through live dashboards drawn directly from SRG's Operations Management System — accurate, current and available to South32 in real time. Secure, cloud-based access for project leaders, South32 representatives and key personnel. Coverage:

  • · Workforce tracking — movements, hours worked, availability
  • · Compliance & VOC status — Pegasus verification, training records
  • · Access system utilisation — scaffold and rope access
  • · Progress against milestones and the maintenance plan
  • · Safety metrics — incidents, near misses, hazard observations
  • · Resource management — equipment usage, stock levels, logistics
Reporting_Scope_and_Access.pdf
Quarterly performance review — terms of reference Scheduled

Quarterly meetings tracking KPIs and safety indicators, addressing non-conformances and upcoming contract events, and identifying improvement opportunities.

QPR_Terms_of_Reference.pdf
Compliance & VOC
Workforce compliance register — Pegasus & VOC Current

Verification of competency and training records for the core team. 100% current as at 19 Jun 2026. Maintained live from the OMS.

VOC_Pegasus_Register.xlsx
Safety & work method
WHS management plan & SWMS library Current

WHS plan, SWMS for scaffold erect/dismantle and hoist recovery, dropped-object controls and exclusion-zone procedures for material recovery at height.

WHS_Management_Plan.pdf SWMS_Scaffold_Hoist_Recovery.pdf
QA/QC & inspection
NDT & inspection readiness (Phase 2) Planned

Forward register for the NDT phase — ITPs, inspection alignment to shutdown windows, and equipment/people utilisation tracking. Populated as Phase 2 mobilises.

NDT_Inspection_Plan_DRAFT.pdf